Photo:
Sparkonline
|
●Over 8,391.06MW lost in
eight days
It may take a longer time
for the country to overcome its electricity supply challenges as the
distribution companies (DisCos) reject generated energy from power plants.
The
Guardian Nigeria report continues:
A
review of the power sector load summary from 13th to 20th August, 2017 by The Guardian showed that an average of
1,000 megawatts (MW) is rejected daily by the Discos, even as electricity
consumers continue to groan in darkness. Specifically, the 11 DisCos
collectively rejected 8, 391.06MW within eight days.
Experts
say that the continuous electricity load rejection could worsen the epileptic
power supply and cause more economic loss to the country.
For
instance, on the 20th of August, a total of 818.01MW was rejected by all the
disCos; 626.97MW, 701.31MW, 1,581.39MW, 1,506.00MW, 1,202.01MW, 1,062.11MW and
890.26MW were rejected on the 19th, 18th, 17th, 16th, 15th, 14th and 13th of
August.
The
situation has resulted in the shortage in power supply in the country.
The
Daily Operational Report from the Transmission Company of Nigeria (TCN) also
revealed that despite having a national peak demand of 19,100MW, the country
was only able to generate 3,264MW on September 7, 2017.
The
report explained that though the country has the capacity to generate 11,165.40MW,
TCN has continued to transmit below its current capability of 7,000MW.
Also,
the Nigerian Electricity Supply Industry Statistics (NESI) disclosed that the
country lost an estimated ₦1.202billion on September 5, 2017 due to several
constraints inhibiting the power sector. NESI put the average power sent out on
September 5, 2017 at 3759MW, while the reported gas constraint was put at 450MW.
It said that the power sector lost 2,055MW to reported frequency management
constraint due to loss of DisCo feeders.
The
power generation companies have continued to lament TCN’s inability to transmit
available power to the distribution companies, which usually result in idle
capacity. For example, Egbin Power PLC puts its idle power at 700MW daily.
Lamenting
the company’s challenges, the Managing Director and Chief Executive, Dallas
Peavey, said the company had been able to overcome the challenge of gas supply,
but had over 700MW of idle power which could not be transmitted to the
distribution companies.
The
Director of Research and Advocacy, Association of Nigerian Electricity
Distributors (ANED), Sunday Oduntan, blamed TCN for its inability to transmit
electricity to the DisCos.
Oduntan
said that the situation would persist as TCN continued to face technical
limitations preventing the wheeling of power to some specific geographical
locations.
“The
issue is about the wrong dumping of load where the DisCos cannot recover the
cost as the power supply is not always enough for all the customers under a
particular DisCo.
“The
truth of the matter is that TCN has not been able to properly transmit the
generated power to the various distribution companies. If my customers are in
Mushin, you cannot take the power to Victoria Island. How do you expect us to
distribute such power? No matter how TCN wants to play it to colour the reality
of transmission shortcomings, transmission remains the weakest link in the
power value chain,” he said.
On
TCN’s capability, the Executive Director, Niger Delta Power Holding Company
(NDPHC), Sanusi Garba, said the evacuation capacity of the company was a major
shortcoming aggravated by the inadequate financing of the firm caused by its
low operating tariff, uncompleted legacy projects and declining budgetary
allocation.
“The
liquidity problem in the sector must be resolved. All technical hitches at the
transmission-distribution interface must be removed. It is vital to reinforce
and expand the distribution infrastructure to take up more power from the
system,” Garba said.
The
General Manager (Public Affairs), Seun Olagunju, said in a statement that TCN
was working assiduously to improve and stabilize grid frequency at 49.75Hz to
50.25Hz. “TCN is working with the Nigerian Electricity Regulatory Commission
(NERC) on the provision of required incentives for generation companies (GenCos)
to provide enough spinning reserve. The company is also committed to taking all
other actions that would lead to sustained system stability,” she said.
The company reiterated its commitment to diligently executing its grid expansion and stability plans in the short, medium and long terms as well as working closely with the GenCos and DisCos to grow the load capability and deliver quality and stable electricity supply to consumers nationwide.
No comments:
Post a Comment