|
It was meant to be a worthy edifice housing the Vice
President and one of the former President Goodluck Jonathan’s administration’s
star projects.
But, with N7billion already spent, the number two citizen’s official home now
seems abandoned, subdued by weeds. The Federal Capital Development Authority
(FCDA) has abandoned the project, following the refusal of the 7th Senate to
accept the inflation of the contract sum by N9 billion. The builders have not
been fully paid despite the release of the N7billion, The Nation learnt. Why they
were shortchanged was not clear yesterday.
The project is yet to
reach 80 per cent completion, contrary to the facts presented to the Senate by
the FCDA.
The contract was awarded
in 2009 at N7billion. But in 2012, a former Minister of the Federal Capital
Territory (FCT) Sen. Bala Mohammed, came with a request for N9billion more to
complete the project.
The variation was
expected to accommodate a helipad. There was public outrage.
The Nation report continues:
FCDA Executive Secretary
Adamu Ismail later told the Senate Committee on FCT that the proposed
additional N9 billion was slashed to about N6 billion by the Bureau for Public
Procurement (BPP).
He said the variation was
also meant to provide furniture, fencing, two additional protocol guest houses,
a banquet hall and security gadgets.
The then Senate Committee
on FCT, led by Senator Smart Adeyemi, however, rejected the request for the
variation, which was more than 100 per cent.
Adeyemi said either N13
billion or N14 billion or N16 billion for the project was “indefensible”.
The abandoned residence
has been overtaken by weeds.
Reptiles are moving
freely at the site.
Although the
weather-beaten red gate was under lock at the weekend, it was learnt that no
fresh work had been done on the site since 2013.
A source said: “The
construction of the VP’s residence has been abandoned by the FCDA since the
Senate turned down the demand for variation.
“Despite the Senate
Committee’s position, the former FCT Minister presented a memo to the Federal
Executive Council (FEC) but ex-President Jonathan said the nation cannot afford
120 per cent variation.
“The former FEC resolved to
complete the project within available budget. This is why the project is
stalled. Definitely, we have a case of abandoned contract at hand.
“The same abandonment is
applicable to the new residences of the President of the Senate and the Speaker
of the House of Representatives.”
A representative of the
construction company, Julius Berger Plc, refused to speak with our
correspondent last night.
The source said: “Go to
those who gave out the job please.”
A presidency source,
said: “The uncompleted residence of the Vice President was not included in the
handover note on the pending issues at the Presidential Villa.
“I think it might be part
of the report of the FCDA. But it is sad that we have to cope with an abandoned
project even at the seat of power.”
The Jonathan
administration left N8,185, 575,211.50 debts at the Presidential Villa.
The report said the
N8.1billion liabilities were outside the expenses on the renovation of the
Defence House, the main residence/ president’s office, Aguda House/ Vice
President’s office and guest houses under the transition programme.
The report said: “The
primary challenge facing the State House has been the inadequacy of successive
budgetary appropriations. The State House annual appropriations do not match
its actual activities, thereby leading to regular recourse to additional
funding from Intervention Fund from the Federal Ministry of Finance.
“About 283 of the
temporary staff not found eligible for regularization were with the approval of
His Excellency, the President given contract appointments renewable annually,
based on performance and fitness.
“However, payment of
their salaries (an average of N8 million per month) is from State House
overheads provision, which remains a huge challenge to State House.
“The existing infrastructure
for mechanical, electrical and associated components have aged and are
performing well beyond their design lives.
“The proposal for their
replacement/ upgrade has been reviewed and certified by the Bureau of Public
Procurement in the total sum of N3,647,793, 305.76. However, due to paucity of
funds, phased implementation is being adopted for the most vital and critical
works, starting with Phase I in the sum of N693, 119,509.55.”
No comments:
Post a Comment